To authorise a planned works programme

Parent Previous Next

The procedure to authorise a planned works programme is as follows:

  1. Navigate to Quick Menu > Planned & Servicing Lite > Management > Planned Program Management. The Planned Program Management window is displayed.
  2. Expand the Awaiting Authorisation status heading and select an associated planned works programme from the alphabetical list, or type its name into the Search Programs field. By default the list is filtered to show All planned programmes. An alternative filter can be applied using the Select view drop-down field: Authorised, Awaiting Authorisation, Cancelled, Complete, Entered, On Hold, Work In Progress, etc. 1.
  3. Click on Authorise Program 2. The status of the planned works programme is set to Authorised.


Note

1 The Search Programs field will match against any element of the planned works programme name.

2 Authorisation permission is only granted to end users with planned programme limit values exceeding the combined sum of all associated SOR template prices for each linked asset.


See related topics...

Planned programme maintenance overview

To create a new planned works programme

To update the status of a planned works programme

To set repair authorisation limits for a user account