The procedure to export a planned works order summary to MS Excel is as follows:
1.
Note
1 Where a file of the same name already exists in the destination folder, the new export report will be annotated with an incremental suffix counter.
Field |
Description |
Planned Program Asset |
The full address of each asset included in the works order generation process. |
Works Order Reference |
The system-generated unique reference number assigned to each individual asset works order. |
Error |
The root cause of any failure encountered during the generation of each individual asset works order. |
See related topics...